Construction time frame information for road safety upgrades along Ghazeepore Road, Waurn Ponds between Colac Rd and Hams Rd, Waurn Ponds.
Breadcrumb
Ghazeepore Road, Waurn Ponds - Road Safety Upgrade Works Timeline

Ghazeepore Road upgrades – works schedule
See what works are still underway (incomplete/upcoming) and which have been completed, including expected traffic and access impacts.
Residents will continue to have access to their properties throughout the works, and garbage collection will remain unaffected.
Incomplete/upcoming works
| Dates | Work item | Work hours | Traffic / pedestrian impacts | Detours / access notes |
| Late April – 30 June 2026 | Remaining works: parking bay indents; single speed hump; concrete splitter island at childcare centre; pedestrian refuges; remaining footpath works; mountable apron at the roundabout, 50km.h signages | 7am-4pm weekdays | Full road closure of Ghazeepore Rd between Sugargum Drive and Colac Road for the duration of the works. The closure is planned from 27 April through to end of June, to ensure safety and efficiency. There are no major impacts to pedestrian access | Bus services/local traffic are required to be detoured for the duration of the closure. VMS signages will be in place to advise road users of changed conditions. |
Completed works
| Dates | Work item | What happened (during works) | Improvements made | |
| 15 July – 12 Aug 2025 | Roundabout construction (Monterey Drive / Ghazeepore Road) | The intersection was fully closed to facilitate construction of the new roundabout. | Safety and traffic flow now improved at the intersection | |
| 17 Sept – 01 Oct 2025 | Bus bay indents | Off-peak (9am–3pm) | Enhances bus operation and traffic flow. Improve accessibility and passenger safety |
If you need assistance on site, please ask one of our works crew who will be happy to help you.
To view the upgrades and reasons behind the works, please visit the following link: https://yoursay.geelongaustralia.com.au/ghazeepore-road-upgrades