These works form part of Council’s ongoing commitment to maintaining and improving local infrastructure. The existing road surface has deteriorated over time due to age, weather conditions and the current width of the road can no longer accommodate rising traffic volumes.

Road Reconstruction & Associated Asphalt Works
Project Details:
Location: Cloverdale Drive - Purnell Road to Kingsley Drive
Dates: July 2026 to late November 2026
Contractor: City of Greater Geelong Construction Unit
Work Hours: Weekdays, 7:00am – 5:00pm (weather permitting)
Project Scope: Reconstruction of the road pavement, new kerb, crossovers and line marking.
Your rubbish collection will not be impacted. Please place your bin out as usual and if required staff will move your bin for collection. We’ll return your bin once it is emptied so please ensure your property number is on your bin to avoid confusion.
Why these works are needed
These works form part of Council’s ongoing commitment to maintaining and improving local infrastructure.
The road surface and pavement have deteriorated over time due to age. These works will provide a stronger, and more durable road that better supports
current and future traffic needs. This project is funded by the Australian Government’s Roads to Recovery/Local Roads Community Infrastructure Program
Traffic Impacts
Full Road Closure
We ask that you follow the detour signs whilst the road is closed.
Stage 1 - Purnell Rd to Cranbourne Drive - August - late September 2026
Stage 2 - Cranbourne Drive to Cathcart Court - Early October 2026 - late November 2026
Asphalt Works
Stage 3 - Cathcart Court to Kingsley Drive - late November 2026
Businesses and residents directly affected will receive further notification two weeks prior to the commencement of works.
Thank you for your patience while we undertake these essential works.