We are redeveloping the Chilwell Library. The library will be closed until August 2026. Scroll down to the 'Stay Updated' section for updates on the development.
Project overview
The Chilwell Library is located in Sladen Park, Russell Street, Newtown on Wadawurrung Country.
We are working with Geelong Regional Libraries and the Chilwell Library Group to undertake a significant redevelopment of the Chilwell Library.
The redevelopment is centred on making sure that Chilwell Library remains an intimate and community-focused facility, improving integration with the park and providing additional spaces for broader community use.
We thank the Victorian Government for the Living Libraries Infrastructure Program grant of $150,000 towards the redevelopment.
During this time, you’re welcome at other library locations including:
- Geelong Library & Heritage Centre (The Dome), 51 Little Malop Street Geelong
- Geelong West Library, 153A Pakington Street Geelong West
- Belmont Library 163 High Street, Belmont
- Highton Library at Roslyn Road (corner Belle Vue Avenue), Highton.
Lifecycle
- Status: Done2022 - Community engagement closes
- Status: Done2022 - Data collated and analysed
- Status: Done2023 - Detailed design development
- Status: Done2024 - Construction tendering
- Status: In Progress2025 - 2026 Construction
Stay Updated
Recent works completed (February 2026 Update):
- Inground services complete
- Slab preparation, including form work and Geo membrane
- Slab poured
- Erection of structural steel complete
- Framing commenced and ongoing
- Measure for windows and doors
Works scheduled for March 2026 include completion of framing, brickwork, installation of windows and doors, and commencing the decking.
Funding project partners
![]()
| ![]() |
Community Consultation

Chilwell Library Redevelopment 
Chilwell Library redevelopment concepts - rear view 
Chilwell Library redevelopment concepts - street view 
Chilwell Library redevelopment concepts - interior view