Construction works
Appendices Construction works Garden beds Irrigation systems Landscape Standards Manual Miscellaneous works Playgrounds and play equipment Practical completion, maintenance and handover Preparatory work Tree management Turf
The Site Superintendent, as identified at this meeting, will then be responsible for all construction works, landscape establishment and maintenance of the site and will be the point of contact for our Officers.
A construction schedule outlining the proposed timing of landscaping components and key milestones should be provided to our Representative at this meeting.
Construction hold-points
During construction of all landscaping, the Site Superintendent must attend the site and sign off on all construction Hold Points. Signed and dated documentation, including photo evidence for all Hold Point inspections must be provided to our Representative prior to Practical Completion.
Hold Point inspections must be undertaken and documented for the items and construction stages as detailed in Table 4: Inspection Hold Points shown opposite on page 29.
Table 4: Inspection Hold Points
| Item | Hold point | Site superintendent inspection required | Documentary and photo evidence required | Council representative inspection required |
|---|---|---|---|---|
| Preliminaries | Pre-Commencement Meeting | Yes | No | Yes |
| Site preparation | Litter and sediment control | Yes | Yes | No |
| Tree protection | Yes | Yes | No | |
| Soil preparation | Yes | Yes | No | |
| Topsoil and soil testing | Yes | Yes | No | |
| Weed eradication | Yes | Yes | No | |
| Garden bed construction | Yes | Yes | No | |
| Planting (trees, garden beds and wetlands) | Stock selection | Yes | No | Possible |
| Site mark-out | Yes | No | Possible | |
| Planting | Yes | Yes | No | |
| Hard infrastructure (all concrete to be form d with steel in place) | Retaining walls | Yes | Yes | Possible |
| Concrete paths/pavement areas | Yes | No | Yes - arrange with Subdivision Inspector | |
| Playground drainage | Yes | Yes | No | |
| Irrigation systems | Layout | Yes | No | No |
| Flushing | Yes | No | No | |
| Commissioning | Yes | No | Yes |
Inspection to be arranged with our Engineering Subdivision Inspector.